Construction Progress

Verified construction progress along the Section 1 corridor, updated monthly.
Overall physical progress for Section 152%Source: Progress meeting, 28 August 2026
Concession signed
12 March 2024
Construction commenced
2 August 2024
Scheduled completion
2 August 2027
Contract duration
1,095 days
Equipment on site
284
Contract variation
Nil

Interchange progress

Select a structure to view its proposed design.

70%
approx. CH 0+500 · T-beam installation and joint concreting works
70%
approx. CH 6+300 · Traffic-diversion wall construction
70%
approx. CH 12+350 · Underpass construction
40%
approx. CH 16+200 · Top-slab structural works

Interchange progress figures are sourced from the client corrections, 14 and 20 September 2026.

Works in progress

Earthworks

Earthworks include site clearance, excavation, replacement of unsuitable materials, rock filling, engineered fill and road formation along the Section 1 corridor.

  • Site clearance76 hectares
  • Topsoil cutting and disposal23,150 m³
  • Cut-to-fill / borrow material650,241 m³
  • Unsuitable-material replacement174,789 m³
  • Rock filling238,375 m³

Cumulative quantities recorded to date in the May 2026 report.

Concrete and structural works

Concrete and reinforcement quantities recorded to date in the May 2026 report.

  • Plain concrete1,902 m³
  • Reinforced concrete17,772 m³
  • Reinforcement steel4,186 tonnes

Drainage and culverts

Box and bridge culverts carry storm flows clear of the carriageway. Status categories are shown as reported; they are not reconciled into a single total to avoid implying a precision the report does not state.

  • Box culverts in the project20
  • Commenced18
  • Completed11
  • Ongoing6
  • Outstanding2

Three bridge / big culverts had commenced; all three were ongoing as of the report.

Footbridges

Ten pedestrian footbridges / crossing points form part of the Section 1 scope. Construction has started at several locations, with the most advanced at CH 12+350, reported at 72%.

View reported footbridge statuses
ChainageReported status
CH 0+08020%
CH 0+853.6Not yet reported
CH 4+490Not yet reported
CH 6+30057%
CH 8+05025%
CH 8+88544.5%
CH 9+92055%
CH 12+35072%
CH 16+20034%
CH 18+2957%

Recent construction activity

What has been built recently along the corridor, in pictures.

  • Underpass construction at Community 18 Interchange, Km 12+350, showing the completed reinforced-concrete box on both sides of the corridor
    Underpass structure completedCommunity 18 Interchange
  • Construction of traffic-diversion walls on the left-hand side at Teshie Link Interchange, Km 6+363, with traffic passing between Accra and Tema
    Traffic diversion walls builtTeshie Link Interchange
  • Precast T-beams for bridge deck construction on the corridor
    Bridge beams cast and placedAlong the Section 1 corridor
  • Pedestrian footbridge No. 5 under construction at Km 8+050, left-hand side
    Pedestrian footbridge going upNear Km 8+050
  • Retaining wall construction at Km 12+120, left-hand side
    Retaining walls under constructionNear Km 12+120
  • Sub-base laying between Km 7+600 and Km 7+980, left-hand side
    New road foundation being laidBetween Km 7+600 and Km 8+340

This month and next

Completed in August 2026

  • Physical progress reached 52%, up from 50% in July.
  • Traffic-diversion and footing walls constructed at Teshie Link Interchange (Km 6+363–6+380).
  • Footing walls and underpass construction at Community 18 Interchange (Km 12+010–12+910).
  • Bridge works advanced at Km 10+873, Km 13+745 and Km 16+556.
  • Subgrade and sub-base laid between Km 7+600 and Km 18+300.
  • Construction of traffic-diversion walls on the left-hand side at Teshie Link Interchange, Km 6+363, with traffic passing between Accra and Tema
  • Footing wall construction on the right-hand side at Teshie Link Interchange, Km 6+380, with an excavator working alongside the corridor
  • Footing wall construction on the right-hand side at Community 18 Interchange between Km 12+010 and Km 12+910, with live traffic in both directions
  • Underpass construction at Community 18 Interchange, Km 12+350, showing the completed reinforced-concrete box on both sides of the corridor
  • Maripoma chart of physical progress for the 19.5 km Section 1 works, rising month by month from 38% in January 2026 to 52% in August 2026

Planned for September 2026

  • Rock filling — 70,000 m³.
  • Natural gravel sub-base — 3,000 m³.
  • Graded crushed stone sub-base — 1,000 m³.
  • Trapezoidal concrete drain — 2,000 m, and U-drain slab — 1,000 m.
  • Continued works at Lashibi Interchange, the footbridges and the box culverts.

Construction considerations

Traffic management

Construction activities can create temporary congestion. The project uses traffic-management plans, alternative routing, signage and public awareness measures.

Dust and environmental management

The report identifies dust and emissions as an environmental consideration. Mitigation measures include water spraying, equipment management and environmental monitoring.

Utilities and right-of-way coordination

Relocation of electricity and water infrastructure remains part of the construction coordination process.

Milestone timeline

  1. 12 March 2024
    Concession signed
  2. 2 August 2024
    EPC Commences36-month window begins
  3. August 2026Current
    52% completeLatest Monthly Progress Report
  4. 2 August 2027
    Scheduled completion