Underpass construction at Km 2+701

Construction Progress

Verified construction progress along the Section 1 corridor, updated monthly.
Overall physical progress for Section 153%Source: Progress report, 7 October 2026
Concession signed
12 March 2024
Construction commenced
2 August 2024
Scheduled completion
2 August 2027
Contract duration
1,095 days
Equipment on site
284
Contract variation
Nil

Interchange progress

Select a structure to view its proposed design.

95%
approx. CH 0+500 · T-beam installation and joint concreting works
92%
approx. CH 6+300 · Traffic-diversion wall construction
93%
approx. CH 12+350 · Underpass construction
40%
approx. CH 16+200 · Top-slab structural works

Interchange progress figures are sourced from the Progress report, 7 October 2026.

Works in progress

Earthworks

Earthworks include site clearance, excavation, replacement of unsuitable materials, rock filling, engineered fill and road formation along the Section 1 corridor.

  • Site clearance76 hectares
  • Topsoil cutting and disposal23,150 m³
  • Cut-to-fill / borrow material650,241 m³
  • Unsuitable-material replacement174,789 m³
  • Rock filling238,375 m³

Cumulative quantities recorded to date in the May 2026 report.

Concrete and structural works

Concrete and reinforcement quantities recorded to date in the May 2026 report.

  • Plain concrete1,902 m³
  • Reinforced concrete17,772 m³
  • Reinforcement steel4,186 tonnes

Drainage and culverts

Box and bridge culverts carry storm flows clear of the carriageway. Status categories are shown as reported; they are not reconciled into a single total to avoid implying a precision the report does not state.

  • Box culverts in the project20
  • Commenced18
  • Completed11
  • Ongoing6
  • Outstanding2

Three bridge / big culverts had commenced; all three were ongoing as of the report.

Footbridges

Ten pedestrian footbridges / crossing points form part of the Section 1 scope. Construction has started at several locations, with the most advanced at CH 12+350, reported at 72%.

View reported footbridge statuses
ChainageReported status
CH 0+08020%
CH 0+853.6Not yet reported
CH 4+490Not yet reported
CH 6+30057%
CH 8+05025%
CH 8+88544.5%
CH 9+92055%
CH 12+35072%
CH 16+20034%
CH 18+2957%

Recent construction activity

What has been built recently along the corridor, in pictures.

  • Underpass construction at Community 18 Interchange, Km 12+350, showing the completed reinforced-concrete box on both sides of the corridor
    Underpass structure completedCommunity 18 Interchange
  • Construction of traffic-diversion walls on the left-hand side at Teshie Link Interchange, Km 6+363, with traffic passing between Accra and Tema
    Traffic diversion walls builtTeshie Link Interchange
  • Precast T-beams for bridge deck construction on the corridor
    Bridge beams cast and placedAlong the Section 1 corridor
  • Pedestrian footbridge No. 5 under construction at Km 8+050, left-hand side
    Pedestrian footbridge going upNear Km 8+050
  • Retaining wall construction at Km 12+120, left-hand side
    Retaining walls under constructionNear Km 12+120
  • Sub-base laying between Km 7+600 and Km 7+980, left-hand side
    New road foundation being laidBetween Km 7+600 and Km 8+340

This month and next

Work done for the month of September

  • Physical progress 53%, up from 52% in August.
  • Traffic diversion and footing walls constructed at Lachibi Interchange (km 16+200)
  • T-beam installation for Bridge at km 10+873 (LHS*RHS)
  • Casting of surface concrete and approach slab for Bridge at km 10+873 (LHS*RHS)
  • Construction of piles and pier caps for Bridge at km 13+745-LHS
  • Formwork and reinforcement for Abutment at km 13+745 Bridge-LHS
  • Construction of U-shaped ramp for Footbridge No. 5 at km 8+050 – LHS
  • Formwork and reinforcement for Footbridge No. 7 at km 9+920 -RHS
  • Subgrade laid between 16+600 and 18+300
  • Construction of Lashibi interchange- Median section.
  • U-drain construction – 1000 m
  • Sub-base +crushed stone laid (0/40 mm- 2 layers) from 1+000 -5+500
Bridge and interchange completion, September 2026
Bridge and interchange completion, September 2026
#BridgeEarthworks %Structure %Earthworks CompletionStructure CompletionTotal complettion
1Tetteh Quarshie5%95%0%95%95%
2Teshie Link10%90%2%90%92%
3Community 1810%90%3%90%93%
4Lashibi15%85%0%40%40%

Work planned for October

  • Rock filling - 70,000 m³.
  • Natural gravel sub-base - 3,000 m³.
  • Graded crushed stone sub-base - 2,000 m³.
  • Graded Crushed Stone Base - 2,000 m³.
  • Trapezoidal concrete drain - 2,000 m, and U-drain - 1,000 m.
  • T–beam installation for Lachibi Interchange at km 16+200.
  • Pier construction for footbridge No. 1 at km 0+000
  • Piling for footbridge No. 2 at km 0+860.
  • Continuous work on Footbridge No. 3 at km 4+655 ( U shaped Ramp)
  • Continuous work on Footbridge No. 5 at km 8+050 (Stairs).
  • Continuous work on Footbridge No. 10 at km 18+295 (Formwork and reinforcement).
Footbridge chainages — percentage complete and planned
Footbridge chainages — percentage complete and planned
NbrFootbridges-ChainagesPercentage of previous completed workPercentage done for SeptemberPercentage planned for October
1CH 0+00026%2%15%
2CH 0+860-5%10%
3CH 4+6553%2%10%
5CH 8+05035%40%15%
6CH 8+88545%50%10%
7CH 9+92052%10%-
10CH 18+29525%5%10%

Construction considerations

Traffic management

Construction activities can create temporary congestion. The project uses traffic-management plans, alternative routing, signage and public awareness measures.

Dust and environmental management

The report identifies dust and emissions as an environmental consideration. Mitigation measures include water spraying, equipment management and environmental monitoring.

Utilities and right-of-way coordination

Relocation of electricity and water infrastructure remains part of the construction coordination process.

Milestone timeline

  1. 12 March 2024
    Concession signed
  2. 2 August 2024
    EPC Commences36-month window begins
  3. September 2026Current
    53% completeLatest Monthly Progress Report
  4. 2 August 2027
    Scheduled completion